Morrison’s Superstore 

RG Group

X

OVERVIEW

 

SITE:

Morrisons Superstore - Verwood

 

 VALUE:

£3.2m

 

DATE:

2014 - 2015

 

CONTRACT:

Demolition and Groundworks of leisure centre and shopping precinct

Contract:

  • Demolition of existing leisure centre & shopping precinct.
  • Crushing for re-use on site
  • Remediation of contaminated ground
    All groundworks associated with new superstore construction.
  • Installation of Interceptors.
  • Superstore floor slab
  • Maintaining existing trading superstore throughout our works, demolishing upon completion to facilitate new carpark and petrol filling station.

 

What we did:

Assisted our client & Morrison’s throughout the duration of the project.

Ensuring the existing store remained trading with no disruption.

 

Outstanding results:

HWM Contracting Ltd delivered this challenging project on budget and on time.

Interim and final measurements were progressed during the contact with the final account agreement achieved at the end of the project. 

HWM Contracting Ltd is a key Contractor for  RG Group & we are currently partnering on several schemes at tender stage.

Tesco Superstore & 278 Streetworks 

Vinci Retail 

X

OVERVIEW

 

SITE:

Tesco Superstore - Kinson

 

 VALUE:

£3.55

 

DATE:

2014 - 2015

 

CONTRACT:

Site clearance, groundworks and roadwork infrastructure

 

Contract:

  • Site Clearance
  • Topsoil Screening for re-use
    All groundworks associated with new superstore construction.
  • Superstore floor slab, dock leveller & service yard
  • Maintaining surrounding road network during major 278 streetworks.
  • Working with the existing local businesses to ensure disruption was kept to a minimum.

 

What we did:

Assisted our client, Tesco’s & the local borough council throughout the duration of the project.

Ensuring the new store was completed and opened on the official dates set.

 

Outstanding results:

HWM Contracting Ltd delivered this challenging project on budget and on time.

Interim and final measurements were progressed during the contact with the final account agreement achieved at the end of the project. 

HWM Contracting Ltd is a key Contractor for  Vinci Construction’s Retail business & we are  currently tendering a larger scheme at Bournemouth Airport with them.    

King George V Dry Dock 

S Norton & Co

X

OVERVIEW

 

SITE:

East Side – King George V Dry Dock 

 

 VALUE:

£1m

 

DATE:

2013

 

CONTRACT:

Location, minimisation & removal of hazardous  soils.

 

 

Contract:

  • Break out existing hard standings
  • Crushing for re-use on site
    Highmast construction
  • Installation of 2 x NS200 Interceptors
    10,000m2 Concrete paving
  • 750m of surface water drainage
  • New outfall
  • Construction of Shear slab & building
  • Heavy duty perimeter fencing installation
  • Electrical Sub-contract package let to Rigfone.

What we did:

Worked closely with our client to value engineer and programme the project. 

Outstanding results:

In association with Solent Stevedores & S Norton site teams, we completed the contract and extra works within the contract period and on budget.

Interim and final measurements were progressed during the contact with the final account agreement achieved within two weeks of handover.

HWM Contracting Ltd is a key Contractor for S Norton & Co & we have had repeat business from this client.

shopify stats